Thursday, February 28, 2008

Weekly Report # 9


A. Work Performed During the Week of January 11th 2007 to January 18th 2008








• Start the underground electric installation in the north building pad.

• Install the vapor barrier on the north building pad.

• Continue rough in on the south building pad.

• Install the forms for the concrete pad.

• Schedule concrete pour for the north building pad.

• Pressure grout the existing water line.

• Continue working on the submittal process.


B. Work to be Performed the Week of January 18th 2008 to January 25th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

• Start interior piping work, (water and gas).

• Start the interior electric layout.

• Install the plumbing in the south building pad (underslab).

• Install electric in the south building pad (underslab).

• Install the 3/4” clean stone.

• Prepare the slab for concrete.