Thursday, February 28, 2008

Weekly Report # 8






A. Work Performed During the Week of January 4th 2007 to January 11th 2008


•Continue the masonry work on the new south addition foundation.

•Continue installation of the north building underground plumbing.

•Continue the delivery of materials.

•Continue the installation of the new water pipe, there is a water shut
down scheduled for the 11th to connect the new water pipe.


B. Work to be Performed the Week of January 11th 2008 to January 18th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

•Start the underground electric installation in the north building pad.

•Install the vapor barrier on the north building pad.

•Continue rough in on the south building pad.

•Schedule concrete pour for the north building pad.

•Continue working on the submittal process.