A. Work Performed During the Week of December 14th 2007 to December 21st 2007
- Start building the south addition footings.
- Compact the north building pad.
- Continue the submittal process.
- Accept materials for the new underground retention basin.
- Install the new water valves.
- Install underground structures.
B. Work to be Performed the Week of December 21st 2007 to December 28th 2007
The items of work listed below are contingent upon previous work being completed and weather conditions
- Compaction testing for the north and south building slabs.
- Pour concrete for the south building footings.
- Start the installation of the new water piping.
- Start installing the underground piping in the north building slab.
This is a short week due to the Holidays.