A. Work Performed During the Week of January 21st 2007 to January 25th 2008
• Start interior piping work, (water and gas).
• Start the interior electric layout.
• Install the plumbing in the south building pad (underslab).
• Install electric in the south building pad (underslab).
• Install the 3/4” clean stone.
• Prepare the slab for concrete.
B. Work to be Performed the Week of January 28th 2008 to February 1st 2008
The items of work listed below are contingent upon previous work being completed and weather conditions
• Continue the submittal process.
• Continue work on the interior water and gas pipes.
• Work on the south building pad.
• Install underground structures.
• Survey the new site layout.