A. Work Performed During the Week of November 23rd 2007 to November 30th 2007

•Continue the submittal process.
•Continue clearing the plants for the new front parking lot.
•Prepare the south building pad.
•Prepare the south construction entrance.
•Investigate and locate underground utilities.
•Excavate and pour the footing concrete, north bldg pad.
•Start the block foundation work, north bldg pad.

B. Work to be Performed the Week of November 30th 2007 to December 7th 2007

The items of work listed below are contingent upon previous work being completed and weather conditions

•Continue the Submittal process.
•Continue the block foundation work, north bldg pad.
•Excavate and pour the concrete for the interior column pads.
•Start the removal of the brick veneer, north side only.
•Acquire all needed inspections to proceed with the work.