Weekly Report # 11



A. Work Performed During the Week of January 28th 2007 to February 1st 2008




• Continue the submittal process.
• Continue work on the interior water and gas pipes.
• Work on the south building pad.
• Install underground structures.
• Survey the new site layout.


B. Work to be Performed the Week of February 4th 2008 to February 8th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

• Continue the submittal process.
• Masons to work on the south building pad, preparing the column piers
for the new steel. This process has slowed down due to the weather freezing the ground.
• Install underground structures.
• Survey the new site layout.