A. Work Performed During the Week of November 30th 2007 to December 7th 2007
• Continue the submittal process.
• Continue the foundation block work.
• Accept new materials being delivered to the site.
• Excavate, install rebar, inspect and pour the concrete for the interior
piers.• Install the interior perimeter insulation.
B. Work to be Performed the Week of December 7th 2007 to December 14th 2007
The items of work listed below are contingent upon previous work being completed
and weather conditions
• Continue the submittal process; this will be ongoing for most of the
project.• Locate the existing utility lines.
• Compact to slab foundation.
• Start the removal of the existing face brick on the north side of the
building.• Start the new underground utility installation.