A. Work Performed During the Week of
• Continue with the submittal process.
• Locate the existing underground sprinkler system, remove and mark for future installation.
• Remove plants as required for the new construction.
• Relocate playground equipment.
• Start to strip to top soil.
• Start the location of the existing underground utilities.
• Relocate shed.
• Relocate and reassemble playground equipment.
• Remove catch basin and pipe in the south building footprint.
• Remove sprinkler pump and store in the shed.
B. Work to be Performed the Week of
• Start to grade the south construction area.
• Clear vegetation for the parking lot.
• Survey and stake out the north building footprint.
• Install imported fill for the north building addition.
• Prepare for the installation of the north building footings.
• Continue the submittal process.
• Review the access for the south building addition.
C. Construction Photographs (see link above)
• Start stripping the top soil, north side.
• Locating the existing sprinkler lines, North side of the building.
•South side plant removal as required to erect the building.
R. Muller, Epic Management Inc.