Wednesday, March 5, 2008

Weekly Report #14


A. Work Performed During the Week of February 25th 2008 to February 29th 2008






  • Continue the submittal process.
  • Receive the steel for the south addition.
  • Start the erection of the steel, south addition.

B. Work to be Performed the Week of March 3rd 2008 to March 7 th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions

  • Continue the submittal process.
  • Continue the steel erection for the south addition.

Weekly Report #13













A. Work Performed During the Week of February 18th 2008 to February 22nd 2008

  • Continue the submittal process.
  • Work on the south building pad.
  • Survey the new site layout.

B. Work to be Performed the Week of February 25th 2008 to February 29 th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions

  • Continue the submittal process.
  • Deliver the new steel for the south building addition.
  • Start the steel erection on the south building addition.

Thursday, February 28, 2008

Weekly Report # 12


A. Work Performed During the Week of January 28th 2008 to February 1st 2008

• Continue the submittal process.
• Work on the south building pad.
• Survey the new site layout.

B. Work to be Performed the Week of February 4th2008 to February 8th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

• Continue the submittal process.
• Masons to work on the south building

Weekly Report # 11



A. Work Performed During the Week of January 28th 2007 to February 1st 2008




• Continue the submittal process.
• Continue work on the interior water and gas pipes.
• Work on the south building pad.
• Install underground structures.
• Survey the new site layout.


B. Work to be Performed the Week of February 4th 2008 to February 8th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

• Continue the submittal process.
• Masons to work on the south building pad, preparing the column piers
for the new steel. This process has slowed down due to the weather freezing the ground.
• Install underground structures.
• Survey the new site layout.

Weekly Report # 10


A. Work Performed During the Week of January 21st 2007 to January 25th 2008





• Start interior piping work, (water and gas).
• Start the interior electric layout.
• Install the plumbing in the south building pad (underslab).
• Install electric in the south building pad (underslab).
• Install the 3/4” clean stone.
• Prepare the slab for concrete.

B. Work to be Performed the Week of January 28th 2008 to February 1st 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

• Continue the submittal process.
• Continue work on the interior water and gas pipes.
• Work on the south building pad.
• Install underground structures.
• Survey the new site layout.

Weekly Report # 9


A. Work Performed During the Week of January 11th 2007 to January 18th 2008








• Start the underground electric installation in the north building pad.

• Install the vapor barrier on the north building pad.

• Continue rough in on the south building pad.

• Install the forms for the concrete pad.

• Schedule concrete pour for the north building pad.

• Pressure grout the existing water line.

• Continue working on the submittal process.


B. Work to be Performed the Week of January 18th 2008 to January 25th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

• Start interior piping work, (water and gas).

• Start the interior electric layout.

• Install the plumbing in the south building pad (underslab).

• Install electric in the south building pad (underslab).

• Install the 3/4” clean stone.

• Prepare the slab for concrete.

Weekly Report # 8






A. Work Performed During the Week of January 4th 2007 to January 11th 2008


•Continue the masonry work on the new south addition foundation.

•Continue installation of the north building underground plumbing.

•Continue the delivery of materials.

•Continue the installation of the new water pipe, there is a water shut
down scheduled for the 11th to connect the new water pipe.


B. Work to be Performed the Week of January 11th 2008 to January 18th 2008

The items of work listed below are contingent upon previous work being completed and weather conditions

•Start the underground electric installation in the north building pad.

•Install the vapor barrier on the north building pad.

•Continue rough in on the south building pad.

•Schedule concrete pour for the north building pad.

•Continue working on the submittal process.