A. Work Performed During the Week of April 14th 2008 to April 18th 2008
- Complete the structural steel erection (phase one) on the north addition.
- Start the light gauge framing, north addition.
- Start the rough‐ins for the electrical, plumbing, fire sprinkler piping and the new ductwork, north addition.
- Start the installation of the new roofing, south addition.
- Continue the installation of the densglass siding.
- Start the concrete curbing by the new parking lot and the new entrance.
- Block off the new front entrance with orange fencing.
B. Work to be Performed the Week of April 21st 2008 to April 25th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Continue work on the new parking lot.
- Continue work on the new front entrance.
- Start the interior light gauge framing in the north addition.
- Inspect the structural steel for plumb and square.
- Continue with the exterior siding, south addition.
- Complete the first phase of the roofing for the south addition.
- Continue with the rough electric, plumbing, ductwork and fire sprinkler installation on the south addition