A. Work Performed During the Week of April 7th 2008 to April 11th 2008
- Continue the light gauge framing on the south addition.
- Continue the rough electrical installation, south addition.
- Continue the rough plumbing installation, south addition.
- Continue the installation of the new ductwork, south addition.
- Install the new fire sprinkler lines, south addition.
- Continue the erection, bolting and welding on the north addition structural steel.
- Install the densglass siding on the upper section of the framing on the south addition.
B. Work to be Performed the Week of April 14th 2008 to April 18th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Complete the structural steel erection (phase one) on the north addition.
- Start the light gauge framing, north addition.
- Start the rough‐ins for the electrical, plumbing, fire sprinkler piping and the new ductwork, north addition.
- Start the installation of the new roofing, south addition.
- Continue the installation of the densglass siding.