Weekly Report # 17


A. Work Performed During the Week of March 24th 2008 to March 28th 2008





  • Continue the submittal process.
  • Start the metal framing for the interior walls (south).
  • Continue installing the new ductwork (south).
  • Continue installing the new rough electric (south).
  • Continue installing the new roof drain lines and new gas piping (south).
  • Receive the light gauge framing materials for the north addition.

B. Work to be Performed the Week of March 31st 2008 to April 4th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions

  • Continue the submittal process.
  • Continue the interior framing (south).
  • Continue the ductwork installation (south).
  • Continue the rough electric installation (south).
  • Complete the gas piping (south).
  • Prepare for the structural steel delivery (north).