A. Work Performed During the Week of March 3rd 2008 to March 7th 2008
- Continue the submittal process.
- Continue the steel erection for the south addition.
- AEL here to inspect the steel erection.
B. Work to be Performed the Week of March 10th 2008 to March 14 th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions
- Continue the submittal process.
- Continue the steel erection for the south