Saturday, April 19, 2008
Weekly Report # 19

A. Work Performed During the Week of April 14th 2008 to April 18th 2008
- Complete the structural steel erection (phase one) on the north addition.
- Start the light gauge framing, north addition.
- Start the rough‐ins for the electrical, plumbing, fire sprinkler piping and the new ductwork, north addition.
- Start the installation of the new roofing, south addition.
- Continue the installation of the densglass siding.
- Start the concrete curbing by the new parking lot and the new entrance.
- Block off the new front entrance with orange fencing.
B. Work to be Performed the Week of April 21st 2008 to April 25th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Continue work on the new parking lot.
- Continue work on the new front entrance.
- Start the interior light gauge framing in the north addition.
- Inspect the structural steel for plumb and square.
- Continue with the exterior siding, south addition.
- Complete the first phase of the roofing for the south addition.
- Continue with the rough electric, plumbing, ductwork and fire sprinkler installation on the south addition
Thursday, April 10, 2008
Weekly Report # 18


A. Work Performed During the Week of April 7th 2008 to April 11th 2008
- Continue the light gauge framing on the south addition.
- Continue the rough electrical installation, south addition.
- Continue the rough plumbing installation, south addition.
- Continue the installation of the new ductwork, south addition.
- Install the new fire sprinkler lines, south addition.
- Continue the erection, bolting and welding on the north addition structural steel.
- Install the densglass siding on the upper section of the framing on the south addition.
B. Work to be Performed the Week of April 14th 2008 to April 18th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Complete the structural steel erection (phase one) on the north addition.
- Start the light gauge framing, north addition.
- Start the rough‐ins for the electrical, plumbing, fire sprinkler piping and the new ductwork, north addition.
- Start the installation of the new roofing, south addition.
- Continue the installation of the densglass siding.
Thursday, April 3, 2008
Weekly Report # 17

A. Work Performed During the Week of March 24th 2008 to March 28th 2008
- Continue the submittal process.
- Start the metal framing for the interior walls (south).
- Continue installing the new ductwork (south).
- Continue installing the new rough electric (south).
- Continue installing the new roof drain lines and new gas piping (south).
- Receive the light gauge framing materials for the north addition.
B. Work to be Performed the Week of March 31st 2008 to April 4th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions
- Continue the submittal process.
- Continue the interior framing (south).
- Continue the ductwork installation (south).
- Continue the rough electric installation (south).
- Complete the gas piping (south).
- Prepare for the structural steel delivery (north).
Weekly Report # 16



A. Work Performed During the Week of March 10th 2008 to March 14th 2008
• Continue the submittal process.
• Continue the steel erection welding for the south addition.
• Install the metal roof decking.
• AEL here to inspect the steel erection.
B. Work to be Performed the Week of March 17th 2008 to March 21st 2008
The items of work listed below are contingent upon previous work being completed and weather conditions
• Continue the submittal process.
• Continue the steel erection welding for the south addition.
• Start the ductwork installation.
• Start the roof drain piping.
Weekly Report # 15

A. Work Performed During the Week of March 3rd 2008 to March 7th 2008
- Continue the submittal process.
- Continue the steel erection for the south addition.
- AEL here to inspect the steel erection.
B. Work to be Performed the Week of March 10th 2008 to March 14 th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions
- Continue the submittal process.
- Continue the steel erection for the south