A. Work Performed During the Week of June 23rd 2008 to June 27th 2008
- Continue with the steel framing on the north addition.
- Continue with the ductwork and installation of the VAV boxes.
- Continue the rough electric installation.
- Continue the rough plumbing and the fire sprinkler piping.
- Install the frame for the new skylight.
- Prepare the new parking lot and new entrance for asphalt base course.
- Complete the new roof over the meeting room.
B. Work to be Performed the Week of June 30th 2008 to July 4th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Complete the light gauge steel framing in the north addition.
- Receive and start the new brickwork on the south addition.
- Continue the rough electric, plumbing and mechanical.
- Complete the new parking lot.
- Re‐direct the traffic flow as per the new design.
- Continue the site work curbing.
- Receive the new window frames.
- Clean and prepare the existing parking areas with new stripping.
- Coordinate the work in the existing office areas.