June 2-June 6, June 9- June 13

Work Performed During the Week of June 2nd 2008 to June 6th 2008
  • Continue the light gauge steel framing.
  • Continue the installation of the ductwork, fire sprinkler lines, plumbing and electric.
  • Start the installation of the roofing for the north addition.
  • Continue the installation of the new parking areas.

B. Work to be Performed the Week of June 9th 2008 to June 13th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.

  • Continue with the steel framing on the north addition.
  • Continue with the ductwork and installation of the VAV boxes.
  • Continue the rough electric installation.
  • Continue the rough plumbing and the fire sprinkler piping.
  • Install the frame for the new skylite.
  • Prepare the new parking lot and new entrance for asphalt base