Thursday, July 24, 2008

July 7-July 18, July 18-July 25









A. Work Performed During the Time Period of July 7th 2008 to July 18th 2008

  • Complete the light gauge steel framing in the north addition.
  • Start the new brickwork on the south addition.
  • Continue the rough electric, plumbing and mechanical.
  • Redirect the traffic flow as per the new design.
  • Continue the site work curbing.

B. Work to be Performed the Time Period of July 18th 2008 to July 25th 2008

These items of work are contingent upon the previous work being completed and the weather conditions.

  • Continue work on the new exit drive by the Police Station.
  • Continue work on the drop off Window Island.
  • Continue the masonry (brickwork).
  • Continue the roof tie in to the existing roof.
  • Start the installation of the new windows.
  • Start the installation of the new door frames.
  • Continue the electric installations, various areas.
  • Continue the mechanical, plumbing and hvac installations.