A. Work Performed During the Time Period of
- Install drywall in the north and south additions.
- Review and inspect that all required items have been installed before the drywall is applied.
- Start the site clean‐up in preparation for landscaping.
- Clean‐up the interior of the new additions.
- Pour the concrete pads for the new concrete walkways.
- Continue the work for the existing office areas.
B. Work to be Performed the Time Period of August 25th 2008 to August 29th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Continue the drywall installation.
- Spackle and sand the drywall.
- Start paint application in various areas.
- Complete the window frame and glazing installation.
- Continue the site work
- Near completion of the existing office area renovation.
- Accept the delivery of the finish materials.