Thursday, July 24, 2008

July 7-July 18, July 18-July 25









A. Work Performed During the Time Period of July 7th 2008 to July 18th 2008

  • Complete the light gauge steel framing in the north addition.
  • Start the new brickwork on the south addition.
  • Continue the rough electric, plumbing and mechanical.
  • Redirect the traffic flow as per the new design.
  • Continue the site work curbing.

B. Work to be Performed the Time Period of July 18th 2008 to July 25th 2008

These items of work are contingent upon the previous work being completed and the weather conditions.

  • Continue work on the new exit drive by the Police Station.
  • Continue work on the drop off Window Island.
  • Continue the masonry (brickwork).
  • Continue the roof tie in to the existing roof.
  • Start the installation of the new windows.
  • Start the installation of the new door frames.
  • Continue the electric installations, various areas.
  • Continue the mechanical, plumbing and hvac installations.

Thursday, July 3, 2008

June 23rd - June 27th, June 30th - July 4th















A. Work Performed During the Week of June 23rd 2008 to June 27th 2008
  • Continue with the steel framing on the north addition.
  • Continue with the ductwork and installation of the VAV boxes.
  • Continue the rough electric installation.
  • Continue the rough plumbing and the fire sprinkler piping.
  • Install the frame for the new skylight.
  • Prepare the new parking lot and new entrance for asphalt base course.
  • Complete the new roof over the meeting room.


B. Work to be Performed the Week of June 30th 2008 to July 4th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
  • Complete the light gauge steel framing in the north addition.
  • Receive and start the new brickwork on the south addition.
  • Continue the rough electric, plumbing and mechanical.
  • Complete the new parking lot.
  • Re‐direct the traffic flow as per the new design.
  • Continue the site work curbing.
  • Receive the new window frames.
  • Clean and prepare the existing parking areas with new stripping.
  • Coordinate the work in the existing office areas.