Tuesday, September 9, 2008

September 1st - September 5, September 8th - September 12th












A. Work Performed During the Time Period of September 1st 2008 to September 5th 2008
  • Install drywall in the north and south additions.
  • Start the site clean‐up in preparation for landscaping.
  • Clean‐up the interior of the new additions.
  • Continue the work for the existing office areas.
  • Spackle and sand the drywall.
  • Continue panting the finished walls.
  • Continue the installation of the trees and bushes.
  • Start the installation of the new sprinkler system.


B. Work to be Performed the Time Period of September 8th 2008 to September 12th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
  • Continue the paint application in various areas.
  • Complete the window frame and glazing installation.
  • Continue the site work, clean up and finish grading.
  • Near completion of the existing office area renovation.
  • Accept the delivery of the finish materials.
  • Continue the sprinkler system installation.
  • Continue the installation of the new ceilings.
  • Complete the installation of the trees and bushes.
  • Continue to install the exterior site lighting.

August 18th-August 22, August 25th-August 29










A. Work Performed During the Time Period of August 18th 2008 to August 22nd 2008

  • Install drywall in the north and south additions.
  • Review and inspect that all required items have been installed before the drywall is applied.
  • Start the site cleanup in preparation for landscaping.
  • Cleanup the interior of the new additions.
  • Pour the concrete pads for the new concrete walkways.
  • Continue the work for the existing office areas.


B. Work to be Performed the Time Period of August 25th 2008 to August 29th 2008

These items of work are contingent upon the previous work being completed and the weather conditions.

  • Continue the drywall installation.
  • Spackle and sand the drywall.
  • Start paint application in various areas.
  • Complete the window frame and glazing installation.
  • Continue the site work
  • Near completion of the existing office area renovation.
  • Accept the delivery of the finish materials.