A. Work Performed During the Time Period of September 1st 2008 to September 5th 2008
- Install drywall in the north and south additions.
- Start the site clean‐up in preparation for landscaping.
- Clean‐up the interior of the new additions.
- Continue the work for the existing office areas.
- Spackle and sand the drywall.
- Continue panting the finished walls.
- Continue the installation of the trees and bushes.
- Start the installation of the new sprinkler system.
B. Work to be Performed the Time Period of September 8th 2008 to September 12th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
- Continue the paint application in various areas.
- Complete the window frame and glazing installation.
- Continue the site work, clean up and finish grading.
- Near completion of the existing office area renovation.
- Accept the delivery of the finish materials.
- Continue the sprinkler system installation.
- Continue the installation of the new ceilings.
- Complete the installation of the trees and bushes.
- Continue to install the exterior site lighting.