A. Work Performed During the Week of May 2nd 2008 to May 9th 2008
• Fire sprinkler installation on the south addition.
• Start the interior light gauge framing in the north addition.
• Continue with the rough electric.
• Continue the rough plumbing.
• Continue the ductwork.
• Install the densglass siding on the exterior of the south addition.
B. Work to be Performed the Week of May 12th 2008 to May 16th 2008
These items of work are contingent upon the previous work being completed and the weather conditions.
• Continue the steel erection on the north addition.
• Continue the light gauge steel framing on the north addition.
• Start the rough plumbing, rough electric, mechanicals and fire sprinkler piping on the north addition.
• Continue with the submittal process.