Thursday, May 22, 2008

May 19-23, May 25-30










A. Work Performed During the Week of May 19th 2008 to May 23rd 2008

• Complete the steel erection on the north addition.
• Continue the light gauge steel framing on the north addition.
•Start the rough plumbing, rough electric, mechanicals and fire sprinkler piping on the north addition.
• Continue with the submittal process.


B. Work to be Performed the Week of May 25th 2008 to May 30th 2008

These items of work are contingent upon the previous work being completed and the weather conditions.

• Complete the structural steel testing.
• Continue the light gauge steel framing.
• Continue the installation of the ductwork, fire sprinkler lines, plumbing and electric.
• Review and finalize the documentation for the new parking lot design.
• Install the roofing for the north addition.

Thursday, May 15, 2008

Weekly Report # 21










A. Work Performed During the Week of May 2nd 2008 to May 9th 2008

• Fire sprinkler installation on the south addition.
• Start the interior light gauge framing in the north addition.
• Continue with the rough electric.
• Continue the rough plumbing.
• Continue the ductwork.
• Install the densglass siding on the exterior of the south addition.


B. Work to be Performed the Week of May 12th 2008 to May 16th 2008

These items of work are contingent upon the previous work being completed and the weather conditions.

• Continue the steel erection on the north addition.
• Continue the light gauge steel framing on the north addition.
• Start the rough plumbing, rough electric, mechanicals and fire sprinkler piping on the north addition.
• Continue with the submittal process.