Wednesday, March 5, 2008

Weekly Report #14


A. Work Performed During the Week of February 25th 2008 to February 29th 2008






  • Continue the submittal process.
  • Receive the steel for the south addition.
  • Start the erection of the steel, south addition.

B. Work to be Performed the Week of March 3rd 2008 to March 7 th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions

  • Continue the submittal process.
  • Continue the steel erection for the south addition.

Weekly Report #13













A. Work Performed During the Week of February 18th 2008 to February 22nd 2008

  • Continue the submittal process.
  • Work on the south building pad.
  • Survey the new site layout.

B. Work to be Performed the Week of February 25th 2008 to February 29 th 2008
The items of work listed below are contingent upon previous work being completed and weather conditions

  • Continue the submittal process.
  • Deliver the new steel for the south building addition.
  • Start the steel erection on the south building addition.